How Calculated The Actual Finish field contains 'NA' until there is zero remaining work or you set the task's % Complete field or the task or assignment's % Work Complete field to 100. There are several categories of Actual Finish fields. The Actual Finish field shows the date and time when a task or assignment was actually completed.